title: "Heijunka in CNC Shops: Production Leveling and Heijunka Box"
description: "Heijunka in a CNC shop: level the weekly load on each machine, adapt the heijunka box and follow an example with 3 machines."
image: https://www.jitbase.com/hubfs/heijunka-production-leveling-cnc-shop.webp
---

[+1 438 942-8501](tel:+1%20438%20942-8501)

[Log In](https://app.jitbase.com/)

- [English](https://www.jitbase.com/blog/heijunka-production-leveling-cnc-shop)
- [Français](https://www.jitbase.com/fr/blog/heijunka-lissage-production-atelier-cnc)

[![JITbase black logo](https://www.jitbase.com/hs-fs/hubfs/Logos/jitbase-logo-black-horiz.webp?width=175&height=88&name=jitbase-logo-black-horiz.webp)](https://www.jitbase.com/homepage-archive)

- Solutions

   Back

  ##### [Machine Monitoring](https://www.jitbase.com/machine-monitoring)

    - ##### [Machine Monitoring](https://www.jitbase.com/machine-monitoring)
  
  Back
  
  ##### [Production Planning](https://www.jitbase.com/production-planning)

    - ##### [Production Planning](https://www.jitbase.com/production-planning)
  
  Back
  
  ##### [Edge Platform](https://www.jitbase.com/edge-platform)

    - ##### [Edge Platform](https://www.jitbase.com/edge-platform)
  
  Back
- Resources

   Back

  ##### [Our Downloadable Resources](https://www.jitbase.com/download)

    - ##### [Our Downloadable Resources](https://www.jitbase.com/download)
  
  Back
  
    - [Case Studies](https://jitbase.com/download#case-studies)
    - [White Papers](https://jitbase.com/download#white-papers)
    - [Brochures](https://jitbase.com/download#brochures)
    - [Product & Integration](https://jitbase.com/download#Product-Integration)
    - [In the Media](https://jitbase.com/download#in-the-media)
  
  ##### [Blog](https://www.jitbase.com/blog)

    - ##### [Blog](https://www.jitbase.com/blog)
  
  Back
  
    - [Machine Monitoring](https://www.jitbase.com/blog/tag/machine-monitoring)
    - [Labor Management](https://www.jitbase.com/blog/tag/labor-management)
    - [Production Planning and Scheduling](https://www.jitbase.com/blog/tag/production-planning-and-scheduling)
    - [Quality and Inspection](https://www.jitbase.com/blog/tag/quality-and-inspection)
- [Pricing](https://www.jitbase.com/pricing)

[Connect Machines for Free](https://sso.jitbase.com/realms/webapp/protocol/openid-connect/registrations?client_id=website-registration&response_type=code&scope=openid&redirect_uri=https://admin.jitbase.com)

[+1 438 942-8501](tel:+1%20438%20942-8501) [Log In](https://app.jitbase.com/)

- [English](https://www.jitbase.com/blog/heijunka-production-leveling-cnc-shop)
- [Français](https://www.jitbase.com/fr/blog/heijunka-lissage-production-atelier-cnc)

  

[Book a demo](https://www.jitbase.com/demo-archive) [Connect Machines for Free](https://sso.jitbase.com/realms/webapp/protocol/openid-connect/registrations?client_id=website-registration&response_type=code&scope=openid&redirect_uri=https://admin.jitbase.com)

![Production supervisor and CNC machinist with a tablet reviewing the weekly machine load on a shop floor screen: heijunka with JITbase](https://www.jitbase.com/hubfs/heijunka-production-leveling-cnc-shop.webp)

 Blog [Production planning and scheduling](https://www.jitbase.com/blog/tag/production-planning-and-scheduling)

# Heijunka in CNC Shops: Production Leveling and Heijunka Box

[*written by* Judicael Deguenon on November 23, 2026](https://www.jitbase.com/blog/author/judicael-deguenon)

Heijunka is the lean practice of leveling production. It spreads the volume and the mix of work evenly over the days of a week, instead of following the uneven order in which jobs arrive. In a CNC shop, it turns a week of overloaded Mondays and idle Thursdays into a week where every machine carries a steady, realistic load.

This guide explains what heijunka means and why it is harder in a high-mix shop than on an assembly line. It then walks through an example with 3 machines over one week, before and after leveling, and shows how to adapt the heijunka box to a CNC shop. For the wider scheduling method, see [production planning and scheduling for CNC shops](https://www.jitbase.com/blog/production-scheduling-cnc).

## What Is Heijunka?

Heijunka is the Japanese word for leveling. The Lean Enterprise Institute defines it as [leveling the type and quantity of production over a fixed period of time](https://www.lean.org/lexicon-terms/heijunka/). It comes from the Toyota Production System, and lean texts place it in the foundation of that system. In English, it is also called production leveling, production smoothing or level loading.

Heijunka levels two things:

- **Volume:** the total amount of work released each day stays close to the average demand, instead of following daily spikes.
- **Mix:** when the same products are made often, they are spread across the period instead of being grouped in one long run of each part.

Lean names three sources of waste that heijunka targets. Mura is unevenness: a workload that swings from peak to valley. Muri is overburden: machines and people pushed beyond their capacity during the peaks. Muda is the waste that results, such as overtime, waiting, extra inventory and late orders. Heijunka attacks mura first, and muri and muda go down with it.

## Why Production Leveling Is Harder in a High-Mix CNC Shop

Heijunka was built for repetitive production: the same few products every day, with a sequence that can be repeated. A CNC job shop rarely works that way:

- **Few orders repeat.** Many jobs are one-offs or small batches, so there is no stable mix to spread across the week.
- **Setups are long.** Splitting a run into smaller batches multiplies setups, and a CNC setup can take an hour or more.
- **Routings differ by job.** One part goes lathe, then mill, another goes straight to the machining center, so the load moves from machine to machine.
- **Demand is lumpy.** A customer drops three orders on Monday and nothing until the next week.
- **The ERP releases work as it arrives.** Many traditional ERP and MRP plans follow order dates and material needs without checking capacity machine by machine, so the start of the week fills up first.

The answer is not to give up on leveling but to level something else. A job shop cannot repeat a fixed sequence of parts, but it can level the load: the planned hours on each machine and for each operator, day by day. That leveling must still respect routings, due dates and available capacity. Strictly speaking, this is capacity leveling inspired by heijunka rather than the textbook heijunka sequence, and it is the version this guide uses.

**Plan the week around real capacity.** Many ERP plans assume unlimited capacity. JITbase builds the schedule around your machines, operators, shift hours and due dates.

[See finite-capacity scheduling](https://www.jitbase.com/erp-to-finite-capacity-scheduling)

## Heijunka Example: Leveling One Week on 3 Machines

Take a shop with three machines: two CNC lathes and one vertical machining center (VMC). Each machine has one 8-hour shift per day, so 40 hours per week. The work orders for the week total 104 hours of setup and machining. On paper, the week fits: 104 hours of load for 120 hours of capacity, about 87%.

Here is the load requested by the work orders, placed on the day each order arrived, before anyone checks the capacity. Cells marked (over), in red, are above the 8 available hours. Cells marked (low), in yellow, are at half capacity or less:

| Machine | Mon | Tue | Wed | Thu | Fri | Week |
| --- | --- | --- | --- | --- | --- | --- |
| **Lathe 1** | 12 h (over) | 10 h (over) | 6 h | 3 h (low) | 5 h | 36 h |
| **Lathe 2** | 9 h (over) | 8 h | 5 h | 4 h (low) | 6 h | 32 h |
| **VMC** | 10 h (over) | 11 h (over) | 9 h (over) | 2 h (low) | 4 h (low) | 36 h |

The weekly total hides the real problem. Even machine by machine, the week looks fine: Lathe 1 and the VMC are at 90% of their weekly capacity, Lathe 2 at 80%. The trouble only shows day by day. Lathe 1 has 12 hours of work on Monday for 8 available, which no 8-hour shift can run. The VMC has 11 hours on Tuesday. Across the three machines, the work orders ask for 13 hours above capacity on Monday, Tuesday and Wednesday, while 29 machine-hours sit idle, mostly at the end of the week. In practice, the shop pays overtime early in the week, some jobs slip, and the machines wait on Thursday.

Leveling means moving jobs from the peaks to the valleys, without moving any job past its due date. Every job moved below is due on Friday, so running it later in the week is safe:

- **Lathe 1:** a 4-hour job moves from Monday to Thursday, and a 3-hour job from Tuesday to Friday.
- **Lathe 2:** a 2-hour job moves from Monday to Wednesday, and a 2-hour job from Tuesday to Thursday.
- **VMC:** a 3-hour job moves from Monday to Thursday, a 4-hour job from Tuesday to Friday, and a 2-hour job from Wednesday to Thursday.

The leveled week:

| Machine | Mon | Tue | Wed | Thu | Fri | Week |
| --- | --- | --- | --- | --- | --- | --- |
| **Lathe 1** | 8 h | 7 h | 6 h | 7 h | 8 h | 36 h |
| **Lathe 2** | 7 h | 6 h | 7 h | 6 h | 6 h | 32 h |
| **VMC** | 7 h | 7 h | 7 h | 7 h | 8 h | 36 h |

Each machine carries the same total as before, but no day is above 8 hours and no day is below 6. Lathe 1 keeps only 4 open hours in the whole week, so it is the machine to watch. The comparison:

| Measure | Before leveling | After leveling |
| --- | --- | --- |
| **Total load** | 104 h | 104 h |
| **Hours above capacity** | 13 h | 0 h |
| **Idle machine-hours** | 29 h, mostly Thursday and Friday | 16 h, spread across the week |
| **Busiest machine-day** | 12 h (Lathe 1, Monday) | 8 h |
| **Quietest machine-day** | 2 h (VMC, Thursday) | 6 h |

The 16 open hours are now spread across the week instead of piled up on Thursday. That is potential room for a rush job or a breakdown, provided the right machine, operator, tooling and time slot are free. In a real shop, the routing also links the machines: a milling operation cannot move before its turning operation is done. Before moving a job, check its next operation, the material, the fixture and tools, and whether the machine can run the operation. Check the operator load too, since one operator often runs both lathes. Free machine hours are not always usable hours.

The numbers are an illustration. The method works only if the planned hours are close to reality: if standard times are 20% too low, a leveled week is still an overloaded week.

### When a Peak Cannot Be Moved

In the example, every moved job was due on Friday. In a real week, part of the Monday peak is often due on Monday. When a job cannot move later, try these options in order:

1. **Another machine.** Move the operation to a machine that can run it and has open time, if the program, the tooling and an operator are available.
2. **Planned overtime.** Decide the extra hours on Thursday or Friday of the week before, instead of discovering them on Monday at noon.
3. **An earlier start.** Start the job in the valleys of the previous week, when the material and the previous operation are ready.
4. **A new due date.** Call the customer early, while there is still time to agree on a date the shop can hold.

## The Heijunka Box in a CNC Shop

A heijunka box is a visual board that releases leveled work to the floor. In the classic version, described in the Lean Lexicon of the Lean Enterprise Institute, each row is a product and each column is a fixed time interval of the shift. Kanban cards placed in the slots tell the floor what to produce in each interval. A material handler picks up the cards of the current interval and brings them to the process.

The interval is called the pitch. On a repetitive line, it is the takt time multiplied by the pack-out quantity (the number of parts per box). For example, if a part is needed every 2 minutes and goes out in boxes of 10, the pitch is 20 minutes. The box then releases one box of work every 20 minutes, in a mix that matches demand.

A CNC job shop rarely has a takt time per part, so the box is adapted:

| Element | Classic heijunka box | Job-shop version |
| --- | --- | --- |
| **Rows** | One per product or part number | One per machine or machine group |
| **Columns** | Pitch intervals of a shift, for example 20 minutes | Days or half-shifts of the coming week |
| **Contents of a slot** | Kanban cards, one pitch of production each | Jobs with their planned setup and machining hours |
| **Leveling rule** | Same mix and quantity every interval | Planned hours per slot close to the average, never above capacity |
| **Who loads it** | Production control, from customer demand | The planner, from the work orders and their due dates |

Here is the leveled week from the example, drawn as a job-shop heijunka board. It is not a traditional heijunka box: it keeps the same visual leveling principle, but sorts work by machine and day instead of by product and pitch. Each entry is a job with its planned hours, and (moved) marks the jobs taken out of a peak:

| Machine | Mon | Tue | Wed | Thu | Fri |
| --- | --- | --- | --- | --- | --- |
| **Lathe 1** | J201 5 h J202 3 h | J203 7 h | J204 6 h | J205 3 h J206 4 h (moved) | J207 5 h J208 3 h (moved) |
| **Lathe 2** | J211 4 h J212 3 h | J213 6 h | J214 5 h J215 2 h (moved) | J216 4 h J217 2 h (moved) | J218 6 h |
| **VMC** | J221 7 h | J222 4 h J223 3 h | J224 7 h | J225 2 h J226 3 h (moved) J227 2 h (moved) | J228 4 h J229 4 h (moved) |

Many shops start with a whiteboard: one row per machine, one column per day, one magnet per job with its hours written on it. The board makes the overload visible before Monday. It also becomes hard to maintain once the shop has more than a few machines and the plan changes every day.

## How to Level Production in a CNC Shop in 6 Steps

1. **Measure the real load.** For each machine, add up the planned setup and machining hours of the coming week, day by day. Use actual times when standard times are known to be wrong. See [how to quote CNC jobs with standard times](https://www.jitbase.com/blog/cnc-machining-quote-standard-times).
2. **Set the daily capacity.** Count shift hours, minus planned stops, breaks and maintenance. Leave some open hours in the week for rush jobs and breakdowns, instead of filling every day to 100%.
3. **Find the peaks and the valleys.** Mark every machine-day above capacity and every day far below the average. Start with the bottleneck: a peak there delays the whole shop. See [bottleneck analysis in CNC shops](https://www.jitbase.com/blog/bottleneck-analysis-cnc-shops).
4. **Move jobs within their due dates.** Move work from the peaks to the valleys, either later when the due date allows it or earlier when the material and the previous operation are ready. Never push a job past its due date to flatten a curve. See [on-time delivery in CNC shops](https://www.jitbase.com/blog/on-time-delivery-cnc-shops).
5. **Level the mix of repeat parts.** For parts ordered every month, consider smaller batches more often instead of one large run, if the setup time allows it. See [lot sizing for CNC shops](https://www.jitbase.com/blog/lot-sizing-cnc-shops).
6. **Check the operators, then review every week.** A leveled machine plan can still overload an operator who runs two machines. Review the next week every Thursday or Friday, before it starts, and compare planned and actual. See [schedule attainment in CNC shops](https://www.jitbase.com/blog/schedule-attainment-cnc-shops).

Setup time is the limit of leveling. The shorter the setups, the more freely jobs can be split and moved. Shops that reduce setups gain room to level, which is why heijunka and setup reduction usually go together. See [reducing setup time with better scheduling](https://www.jitbase.com/blog/reducing-setup-time-with-better-scheduling).

## Heijunka vs Takt Time, Kanban and Lot Sizing

Heijunka is often confused with other lean tools. Each one answers a different question:

| Concept | Question it answers | Link with heijunka |
| --- | --- | --- |
| **Takt time** | How often must a part be finished to keep up with demand? | Takt time sets the pace, heijunka arranges the work to follow it |
| **Kanban** | When should a process produce or move parts? | A heijunka box releases kanban cards at a steady pace |
| **Lot sizing** | How many parts should run per setup? | Smaller batches make it easier to level the mix, but add setups |
| **Workload balancing** | Is each operator evenly loaded during the shift? | Heijunka levels the load from day to day, balancing spreads it between people within a shift |
| **Production Gantt chart** | Which operation runs on which machine, and when? | The Gantt chart shows the leveled plan, hour by hour |

For more on each tool, see [takt time vs cycle time vs lead time](https://www.jitbase.com/blog/what-is-takt-time-how-to-calculate-and-reduce-it), [kanban vs continuous flow](https://www.jitbase.com/blog/kanban-vs-continuous-flow-wip-software), [lean workload balancing](https://www.jitbase.com/blog/lean-workload-balancing-playbook) and [the production Gantt chart](https://www.jitbase.com/blog/production-gantt-chart-cnc-shop).

## Production Leveling With JITbase

Leveling by hand works for a few machines on a whiteboard. It gets harder when the plan changes several times a day and the routing links the machines. JITbase builds a finite-capacity schedule from your work orders: a schedule that only uses the hours really available on each machine and for each operator. It gives the planner what leveling needs:

- **Planned load by machine, day by day:** you see the load of each machine for each day of the coming week, so the peaks and the valleys are visible before the week starts.
- **Planned load by operator and by shift:** setups, changeovers and manual stops are counted for each operator, so a leveled machine plan does not hide an overloaded person.
- **Drag and drop:** you move an operation to another day or another machine and see the effect on the load right away.
- **Actual times from the machines:** setup and cycle times are collected by job, so the planned hours used for leveling move closer to reality over time.

The Planning screen below shows the operator view: the planned load of one operator for one shift, with setups, changeovers and M00 stops counted.

![JITbase Planning screen with the planned load of an operator for one shift, setups, changeovers and M00 stops included: heijunka with JITbase](https://www.jitbase.com/hs-fs/hubfs/allocation%20op%C3%A9rateur%202.webp?width=800&height=467&name=allocation%20op%C3%A9rateur%202.webp)

Your team still decides which jobs move and when. JITbase shows the effect of each move on the machines and on the operators before the week pays for it.

**Balance the load across machines and operators.** In JITbase, you see the planned load of each machine and each operator, and you move operations with a drag and drop when the week becomes uneven.

[See smart scheduling](https://www.jitbase.com/manual-to-smart-scheduling)

## Key Takeaways

- Heijunka levels the volume and the mix of production over a fixed period, to remove the peaks and valleys of the workload.
- A weekly total that fits capacity can still hide overloaded days and idle days.
- In a high-mix CNC shop, level the planned hours per machine and per operator, day by day, rather than a fixed sequence of parts.
- Move jobs from peaks to valleys within their due dates, and keep a margin for rush jobs and breakdowns.
- Leveling is only as good as the planned hours: correct standard times with actual times from the machines.

**Find out what a steadier week is worth.** Estimate the value of less overtime, fewer idle machines and fewer late orders in your own shop.

[Calculate your return on investment](https://www.jitbase.com/return-on-investment)

## Frequently Asked Questions

### What is heijunka in lean manufacturing?

Heijunka is the Japanese word for leveling. In lean manufacturing, it means spreading the volume and the mix of production evenly over a fixed period, such as a shift, a day or a week. Production no longer follows the uneven order in which demand arrives. It comes from the Toyota Production System, where it is considered one of the foundations of just-in-time production.

The goal is to remove the peaks and valleys in the workload. Peaks lead to overtime, rushed setups and late orders, while valleys leave machines and people idle. A leveled schedule keeps the load close to the average every day, which makes lead times shorter and more predictable and leaves room to absorb a rush job or a breakdown.

### What is a heijunka box?

A heijunka box is a visual scheduling board used to level the mix and volume of production. Each row is a product or a part number, and each column is a fixed time interval of the shift. Kanban cards placed in the slots tell the floor what to make in each interval, so the work is released at a steady pace instead of in large batches.

In a high-mix CNC shop where few orders repeat, the classic box is often adapted. The rows become machines or machine groups, the columns become days or half-shifts, and each card or entry is a job with its planned hours. The principle stays the same: release a leveled amount of work per interval and make any overload visible before it reaches the shop floor.

### What is the difference between heijunka and kanban?

Kanban is a pull signal: a card or a bin tells an upstream process to produce or move parts because downstream has used them. Heijunka decides how the work is spread over time, so that the signals arrive at a steady rate and in a balanced mix. One controls when to produce, the other controls how evenly the demand is presented to production.

The two are often used together. A heijunka box distributes kanban cards at fixed intervals, which keeps the pull system from swinging between overload and starvation. Without leveling, a kanban system passes every spike in demand straight to the machines. Without kanban or another release rule, a leveled plan has no simple way to reach the floor.

### Does heijunka work in a high-mix job shop?

Yes, but not in its textbook form. Heijunka was designed for repetitive production, where the same products are made every day and a fixed sequence can be repeated. A CNC job shop runs many different parts in small quantities, so leveling the exact mix of products is rarely possible or useful.

What works is leveling the load: planned hours per machine and per operator per day. The planner moves jobs within their due dates to flatten the peaks, keeps a margin of open capacity for rush jobs and reviews the coming week before it starts. Repeat parts with steady demand can still be leveled by mix, by running smaller batches more often instead of one large run.

### How do you level production when machines have different capacities?

Reason machine by machine, not with the total hours of the shop. Each machine has its own capacity: its shift hours, its planned stops and, for some, a second shift or unattended running. A total that fits the capacity of the shop can hide one machine at 110% and another at 60%. The free hours of a lathe also cannot run a milling operation.

Start with the bottleneck, the machine with the highest load compared with its own capacity, and level it first. Then look at which operations can run on more than one machine, and move work only to machines that can really run it, with the right program, tooling and operator. Express each day as a percentage of that machine's own capacity, so machines with different hours can be compared on the same scale.

### What is the difference between heijunka and takt time?

Takt time is the pace of customer demand: the available production time divided by the number of units the customer needs. It tells you how often a part must be finished to keep up with demand. Heijunka is the way you arrange the work so that production actually follows that pace instead of swinging between peaks and valleys.

In practice, takt time sets the target rhythm and heijunka builds a schedule that respects it. In a high-mix shop, takt time is hard to define for each part, so the same idea applies to load. The target is the average planned hours per machine per day, and leveling keeps each day close to that average without exceeding capacity.

#### SHARE

[mailto:email@example.com?subject=Mail%20from%20our%20Website](mailto:email@example.com?subject=Mail%20from%20our%20Website)

## Related Articles

[![Production supervisor and CNC machinist reviewing a printed shift schedule next to a CNC lathe: production Gantt chart with JITbase](https://www.jitbase.com/hs-fs/hubfs/production-gantt-chart-cnc-shop.webp?width=352&name=production-gantt-chart-cnc-shop.webp)](https://www.jitbase.com/blog/production-gantt-chart-cnc-shop)

[Production planning and scheduling](https://www.jitbase.com/blog/tag/production-planning-and-scheduling)

### [Production Gantt Chart: Definition and CNC Shop Example](https://www.jitbase.com/blog/production-gantt-chart-cnc-shop)

Read more

[![Production supervisor marking a printed shift schedule on a clipboard between a running CNC machine and a stopped one: schedule attainment with JITbase](https://www.jitbase.com/hs-fs/hubfs/schedule-attainment-cnc-shops.webp?width=352&name=schedule-attainment-cnc-shops.webp)](https://www.jitbase.com/blog/schedule-attainment-cnc-shops)

[Production planning and scheduling](https://www.jitbase.com/blog/tag/production-planning-and-scheduling)

### [Schedule Attainment: Formula and Guide for CNC Shops](https://www.jitbase.com/blog/schedule-attainment-cnc-shops)

Read more

[![Two machinists reviewing a stack of machined parts and measuring a part with a caliper in a CNC shop: bottleneck analysis with JITbase](https://www.jitbase.com/hs-fs/hubfs/bottleneck-analysis-cnc-shops.webp?width=352&name=bottleneck-analysis-cnc-shops.webp)](https://www.jitbase.com/blog/bottleneck-analysis-cnc-shops)

[Production planning and scheduling](https://www.jitbase.com/blog/tag/production-planning-and-scheduling)

### [Bottleneck Analysis in CNC Shops: Find Your Limiting Machine](https://www.jitbase.com/blog/bottleneck-analysis-cnc-shops)

Read more

[![Shop manager standing at a workbench in a small CNC machine shop evaluating monitoring software options — MachineMetrics alternative with JITbase](https://www.jitbase.com/hs-fs/hubfs/blog-images/machinemetrics-alternative-small-cnc-shops-hero.jpg?width=352&name=machinemetrics-alternative-small-cnc-shops-hero.jpg)](https://www.jitbase.com/blog/machinemetrics-alternative-cnc-shops)

[Production planning and scheduling](https://www.jitbase.com/blog/tag/production-planning-and-scheduling)

### [MachineMetrics Alternative for Small CNC Shops (2026)](https://www.jitbase.com/blog/machinemetrics-alternative-cnc-shops)

Read more

[![JITbase block logo](https://www.jitbase.com/hs-fs/hubfs/eca01011d7169e8c6395a8d7eebe802d.webp?width=317&height=158&name=eca01011d7169e8c6395a8d7eebe802d.webp)](https://www.jitbase.com/homepage-archive)

![image-2](https://www.jitbase.com/hs-fs/hubfs/image-2.webp?width=156&height=78&name=image-2.webp)

Solutions

- [Production Monitoring](https://www.jitbase.com/production-monitoring)
- [Scheduling & Workforce Management](https://www.jitbase.com/workforce-management)

<https://linkedin.com/company/jitbase> <https://www.facebook.com/jitbase> <https://www.youtube.com/channel/UC0hNdL3yfYCXDpsvQ65Onzg>

Resources

- [Download](https://www.jitbase.com/download)
- [Education](https://www.jitbase.com/education)
- [Return on Investment](https://www.jitbase.com/return-on-investment)
- [CNC Machines we connect](https://www.jitbase.com/machines-we-connect)

Why JITbase

- [Why JITbase](https://www.jitbase.com/why-jitbase)
- [About Us](https://www.jitbase.com/about-us)
- [Partners](https://www.jitbase.com/partners)
- [Contact Us](https://www.jitbase.com/contact)

[Book a demo](https://www.jitbase.com/demo-archive) [Connect Machines for Free](https://sso.jitbase.com/realms/webapp-ngen/protocol/openid-connect/registrations?client_id=website-frontend&response_type=code&scope=openid%20email&redirect_uri=https://admin.jitbase.com/next-gen)

<https://linkedin.com/company/jitbase> <https://www.facebook.com/jitbase> <https://www.youtube.com/channel/UC0hNdL3yfYCXDpsvQ65Onzg>

© 2026 All rights reserved.

- [Privacy Policy](https://www.jitbase.com/privacy-policy)

```json
{
  "@context" : "https://schema.org",
  "@type" : "BlogPosting",
  "author" : {
    "@type" : "Person",
    "name" : "Judicael Deguenon",
    "url" : "https://www.jitbase.com/blog/author/judicael-deguenon"
  },
  "dateModified" : "2026-11-23T15:37:01.369Z",
  "datePublished" : "2026-11-23T15:37:01.000Z",
  "headline" : "Heijunka in CNC Shops: Production Leveling and Heijunka Box",
  "image" : [ "https://www.jitbase.com/hubfs/heijunka-production-leveling-cnc-shop.webp" ],
  "mainEntityOfPage" : {
    "@id" : "https://www.jitbase.com/blog/heijunka-production-leveling-cnc-shop",
    "@type" : "WebPage"
  },
  "publisher" : {
    "@type" : "Organization",
    "logo" : {
      "@type" : "ImageObject",
      "url" : "https://www.jitbase.com/hubfs/logo%20jitbase%201.svg"
    },
    "name" : "JITbase"
  }
}
```

```json
{
  "@context" : "https://schema.org",
  "@type" : "FAQPage",
  "mainEntity" : [ {
    "@type" : "Question",
    "acceptedAnswer" : {
      "@type" : "Answer",
      "text" : "Heijunka is the Japanese word for leveling. In lean manufacturing, it means spreading the volume and the mix of production evenly over a fixed period, such as a shift, a day or a week. Production no longer follows the uneven order in which demand arrives. It comes from the Toyota Production System, where it is considered one of the foundations of just-in-time production. The goal is to remove the peaks and valleys in the workload. Peaks lead to overtime, rushed setups and late orders, while valleys leave machines and people idle. A leveled schedule keeps the load close to the average every day, which makes lead times shorter and more predictable and leaves room to absorb a rush job or a breakdown."
    },
    "name" : "What is heijunka in lean manufacturing?"
  }, {
    "@type" : "Question",
    "acceptedAnswer" : {
      "@type" : "Answer",
      "text" : "A heijunka box is a visual scheduling board used to level the mix and volume of production. Each row is a product or a part number, and each column is a fixed time interval of the shift. Kanban cards placed in the slots tell the floor what to make in each interval, so the work is released at a steady pace instead of in large batches. In a high-mix CNC shop where few orders repeat, the classic box is often adapted. The rows become machines or machine groups, the columns become days or half-shifts, and each card or entry is a job with its planned hours. The principle stays the same: release a leveled amount of work per interval and make any overload visible before it reaches the shop floor."
    },
    "name" : "What is a heijunka box?"
  }, {
    "@type" : "Question",
    "acceptedAnswer" : {
      "@type" : "Answer",
      "text" : "Kanban is a pull signal: a card or a bin tells an upstream process to produce or move parts because downstream has used them. Heijunka decides how the work is spread over time, so that the signals arrive at a steady rate and in a balanced mix. One controls when to produce, the other controls how evenly the demand is presented to production. The two are often used together. A heijunka box distributes kanban cards at fixed intervals, which keeps the pull system from swinging between overload and starvation. Without leveling, a kanban system passes every spike in demand straight to the machines. Without kanban or another release rule, a leveled plan has no simple way to reach the floor."
    },
    "name" : "What is the difference between heijunka and kanban?"
  }, {
    "@type" : "Question",
    "acceptedAnswer" : {
      "@type" : "Answer",
      "text" : "Yes, but not in its textbook form. Heijunka was designed for repetitive production, where the same products are made every day and a fixed sequence can be repeated. A CNC job shop runs many different parts in small quantities, so leveling the exact mix of products is rarely possible or useful. What works is leveling the load: planned hours per machine and per operator per day. The planner moves jobs within their due dates to flatten the peaks, keeps a margin of open capacity for rush jobs and reviews the coming week before it starts. Repeat parts with steady demand can still be leveled by mix, by running smaller batches more often instead of one large run."
    },
    "name" : "Does heijunka work in a high-mix job shop?"
  }, {
    "@type" : "Question",
    "acceptedAnswer" : {
      "@type" : "Answer",
      "text" : "Reason machine by machine, not with the total hours of the shop. Each machine has its own capacity: its shift hours, its planned stops and, for some, a second shift or unattended running. A total that fits the capacity of the shop can hide one machine at 110% and another at 60%. The free hours of a lathe also cannot run a milling operation. Start with the bottleneck, the machine with the highest load compared with its own capacity, and level it first. Then look at which operations can run on more than one machine, and move work only to machines that can really run it, with the right program, tooling and operator. Express each day as a percentage of that machine's own capacity, so machines with different hours can be compared on the same scale."
    },
    "name" : "How do you level production when machines have different capacities?"
  }, {
    "@type" : "Question",
    "acceptedAnswer" : {
      "@type" : "Answer",
      "text" : "Takt time is the pace of customer demand: the available production time divided by the number of units the customer needs. It tells you how often a part must be finished to keep up with demand. Heijunka is the way you arrange the work so that production actually follows that pace instead of swinging between peaks and valleys. In practice, takt time sets the target rhythm and heijunka builds a schedule that respects it. In a high-mix shop, takt time is hard to define for each part, so the same idea applies to load. The target is the average planned hours per machine per day, and leveling keeps each day close to that average without exceeding capacity."
    },
    "name" : "What is the difference between heijunka and takt time?"
  } ]
}
```